A Bill of Quantities – commonly called a BOQ – is one of the most important documents in any construction project. If you have ever submitted a tender, argued about variation costs, or tried to understand why your project went over budget, you have encountered a situation where a properly prepared BOQ either helped you or was missing when you needed it. This guide explains what a BOQ is, what it contains, and when you need one in the UAE construction market.
What Is a BOQ?
A Bill of Quantities is a document that lists every item of work in a construction project – measured by quantity, described by type, and priced per unit. It is the basis for pricing a tender, valuing completed work, and assessing the cost impact of changes.
A typical BOQ line item looks like this:
- Description: Supply and lay 600x600mm porcelain floor tiles, including adhesive bedding and grout, complete
- Unit: m²
- Quantity: 285
- Rate: AED 95 per m²
- Amount: AED 27,075
Multiply this across every trade and every element of the building – structure, finishes, MEP, external works – and you have a complete BOQ.
What a BOQ Contains
A well-prepared BOQ is divided into sections by trade or work package:
- Preliminary and general items: Site setup, temporary works, insurance, project management
- Substructure: Excavation, piling, foundations, ground slab
- Superstructure: Concrete, formwork, reinforcement, blockwork, structural steel
- Roofing and waterproofing
- External works: Facades, cladding, glazing
- Internal finishes: Plastering, screeds, tiling, painting, suspended ceilings
- Joinery and fittings: Doors, windows, kitchen, wardrobes
- Mechanical works: HVAC, plumbing, drainage, firefighting
- Electrical works: Power, lighting, data, security, DEWA connection
- External works and landscaping
Who Prepares a BOQ?
In the UAE, a BOQ is typically prepared by a quantity surveyor, a technical office, or an estimating consultant. For government projects, the consultant issues a BOQ with the tender documents. For private projects, the contractor often prepares their own BOQ from the drawings for internal budgeting and tender pricing.
When Do You Need a BOQ in UAE Construction?
- Tender pricing: You need a BOQ to price a competitive tender accurately. Without one, you are guessing – and guessing wrong costs you either the contract (too high) or money (too low).
- Project budgeting: A BOQ prepared before construction starts gives you a realistic budget. Most UAE villa projects that go over budget do so because they had no BOQ – only a rate per square foot that excluded key items.
- MBRHE housing loan applications: The Mohammed Bin Rashid Housing Establishment requires a detailed BOQ as part of the loan documentation package.
- Bank financing: Construction finance in the UAE typically requires a BOQ to determine drawdown milestones and verify progress payments.
- Variation valuation: When scope changes on a project, the BOQ unit rates are used to price the variation. Without a BOQ, every variation becomes a negotiation.
- Dispute resolution: If a project ends in a dispute, the BOQ is the primary document used to assess contractor claims and client counterclaims.
BOQ vs Rate Per Square Foot
Most contractors in the UAE can quote a price per square foot. This number is useful as a quick sanity check, but it hides everything that matters: the structural system, the specification level, the site conditions, and what is included or excluded. A project with an unusual structural design, a basement, or high-specification finishes will cost significantly more per square foot than a standard villa – the rate per square foot will not tell you that. A BOQ will.
How to Get a BOQ for Your Project
A BOQ is prepared by measuring quantities from your architectural and structural drawings, then applying unit rates to each item. Buildesk prepares detailed BOQs for villa, residential, and commercial projects across Dubai and the UAE – measured from your drawings, priced at current market rates, and delivered in a format you can use for tendering, client reporting, or MBRHE submission.
Find out more about our BOQ preparation services or contact us to get a quote for your project.